Replacement of the water tower (air conditioning)

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$1.0M
$1,041,600
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 2, 2021(actual)
Construction end
Dec 15, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end18 months lateforecast Jun 30, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59886 in the federal list. How to read these figures.