Renovation of sanitary blocks

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$643,280
Federal share80%

of $804.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 10, 2021(actual)
Construction end
Nov 15, 2021(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jun 1, 2021
  • Construction end2 weeks lateforecast Oct 31, 2021

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59887 in the federal list. How to read these figures.