Renovation of sanitary blocks
Federal contribution
$643,280
Federal share80%
of $804.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- May 10, 2021(actual)
- Construction end
- Nov 15, 2021(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 1, 2021
- Construction end2 weeks lateforecast Oct 31, 2021
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59887 in the federal list. How to read these figures.