Replacing a boiler

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$698,274
Federal share80%

of $872.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 15, 2021(actual)
Construction end
Dec 15, 2022(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2021
  • Construction end2 months lateforecast Sep 30, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59888 in the federal list. How to read these figures.