Renovation of the boiler room

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$1.0M
$1,032,000
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 11, 2022(actual)
Construction end
Aug 30, 2024(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2024