Back to projects

Renovation of the outer casing

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$1.1M
$1,059,520
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 23, 2021(actual)
Construction end
Dec 15, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 1, 2021
  • Construction end12 months lateforecast Dec 2, 2022

Also in Montréal