Renovation of the outer casing
Federal contribution
$1.1M
$1,059,520
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Apr 23, 2021(actual)
- Construction end
- Dec 15, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2021
- Construction end12 months lateforecast Dec 2, 2022