Roof replacement
Federal contribution
$673,005
Federal share80%
of $841.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Aug 20, 2021(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end3 months earlyforecast Nov 27, 2021
Also in Blainville