Back to projects

Roof replacement

Blainville, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$673,005
Federal share80%

of $841.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 22, 2021(actual)
Construction end
Aug 20, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end3 months earlyforecast Nov 27, 2021

Also in Blainville