Replacement of ceilings
Federal contribution
$640,000
Federal share80%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 15, 2021
- Construction end3 months lateforecast Dec 20, 2021
Also in Blainville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59979 in the federal list. How to read these figures.