Replacement of electrical input and emergency lighting
Federal contribution
$550,400
Federal share80%
of $688.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Jun 25, 2021(actual)
- Construction end
- Oct 17, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2021
- Construction end8 weeks earlyforecast Dec 15, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59903 in the federal list. How to read these figures.