Brockville - City Hall Clock Tower Revitalization

Brockville, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$84,506
Federal share80%

of $105.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Brockville
Construction start
Jun 28, 2021(actual)
Construction end
Sep 18, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021

Also in Brockville