Pedestrian Crossover at Huron and Niagara Streets

Collingwood, Ontario

completeActive TransportationCVRIS
Federal contribution
$119,703
Federal share80%

of $149.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Collingwood
Construction start
Aug 23, 2021(actual)
Construction end
Dec 21, 2021(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Jan 28, 2022