Queen Elizabeth Hospital Air Handling Unit #1 and #3

Charlottetown, Prince Edward Island

completeVentilationCVRIS
Federal contribution
$1.0M
$1,000,000
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 14, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Health PEI
Construction start
Oct 25, 2021(actual)
Construction end
Aug 28, 2023(actual)

Against the original forecast

  • Construction end3 months lateforecast May 31, 2023