Back to projects

Bell Park Walkway & Loop Trail Development

Greater Sudbury, Ontario

completeActive TransportationCVRIS
Federal contribution
$411,823
Federal share81%

of $508.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
20222023202420252026
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
City of Greater Sudbury
Construction start
Sep 18, 2023(actual)
Construction end
Dec 31, 2025(actual)

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59966 in the federal list. How to read these figures.