Toronto Accessibility Upgrades
Federal contribution
$2.2M
$2,244,000
Federal share80%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
202220232024
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Toronto
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Jun 11, 2024(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 17, 2021
- Construction end4 months lateforecast Jan 31, 2024