Replacement of the interior finish (phase 4) (Asbestos removal)

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$535,920
Federal share80%

of $669.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 30, 2021(actual)
Construction end
Jan 26, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end7 months earlyforecast Aug 30, 2024

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59977 in the federal list. How to read these figures.