Replacement of fire detection and alarm systems and addition of intercommunication systems

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$347,546
Federal share80%

of $434.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 7, 2021(actual)
Construction end
Jan 27, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2021

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59982 in the federal list. How to read these figures.