Replacement of security and intrusion system and emergency lighting
Federal contribution
$653,600
Federal share80%
of $817.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- May 4, 2023(actual)
- Construction end
- May 16, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 3, 2023
- Construction end4 months earlyforecast Aug 31, 2024
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59983 in the federal list. How to read these figures.