completeActive TransportationCVRIS
Federal contribution
$281,023
Federal share80%

of $351.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Kawartha Lakes
Construction start
Jun 1, 2021(actual)
Construction end
Oct 31, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2021
  • Construction end10 months lateforecast Dec 31, 2021