Toronto Accessibility Upgrades
Federal contribution
$2.4M
$2,400,000
Federal share80%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
202220232024
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Toronto
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Dec 30, 2023(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 3, 2021
- Construction end4 weeks lateforecast Nov 30, 2023