Schedule

Announced and approvedJun 9, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Burlington
Construction start
May 9, 2022(actual)
Construction end
Jul 19, 2023(actual)

Against the original forecast

  • Construction start4 months earlyforecast Sep 12, 2022
  • Construction end4 months lateforecast Mar 31, 2023