Back to projects

Courthouse Windows

Woodstock, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$206,796
Federal share80%

of $258.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Oxford
Construction start
Jul 26, 2021(actual)
Construction end
Nov 18, 2021(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2021