Park Trail Network at the Libro Centre

Amherstburg, Ontario

completeActive TransportationCVRIS
Federal contribution
$210,897
Federal share80%

of $263.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
20222023
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Amherstburg
Construction start
Nov 16, 2022(actual)
Construction end
Dec 15, 2022(actual)

Against the original forecast

  • Construction start16 months lateforecast Jul 15, 2021
  • Construction end11 months lateforecast Dec 31, 2021