Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Cobourg
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Dec 31, 2022(actual)