Alma Street Parkette Shoreline Protections

Amherstburg, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$160,000
Federal share80%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Amherstburg
Construction start
Feb 1, 2023(actual)
Construction end
Jun 30, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Sep 1, 2022
  • Construction end2 months lateforecast Apr 30, 2023