Exhaust Fan Upgrade

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$46,800
Federal share80%

of $58.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
2022
Built
Program
COVID-19 Resilience Stream
Construction start
Jul 27, 2022(actual)
Construction end
Nov 8, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2022
  • Construction end17 months earlyforecast Mar 31, 2024