Upgrading the boiler room
Federal contribution
$1.1M
$1,090,307
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- May 5, 2021(actual)
- Construction end
- Nov 18, 2021(actual)
Against the original forecast
- Construction start5 weeks lateforecast Apr 1, 2021
- Construction end3 weeks lateforecast Oct 31, 2021