Upgrade of the boiler room and replacement of the storm and sanitary drainage network
Federal contribution
$6.6M
$6,641,998
Federal share80%
of $8.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Apr 19, 2022(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 1, 2022
- Construction end15 months earlyforecast Mar 31, 2026
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60065 in the federal list. How to read these figures.