Upgrade of the boiler room and replacement of the storm and sanitary drainage network

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$6.6M
$6,641,998
Federal share80%

of $8.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 19, 2022(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 1, 2022
  • Construction end15 months earlyforecast Mar 31, 2026