Back to projects

Upgrading of the Backflow Prevention Device (BPD), the Meter, the Water Shut-Off System and the Domestic Water Inlet Valve

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$206,400
Federal share80%

of $258.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 11, 2022(actual)
Construction end
Sep 9, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast May 31, 2022
  • Construction end3 months lateforecast Jun 2, 2023