Repair of the heating system and interior finishes
Federal contribution
$52,339
Federal share65%
of $80.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Oct 31, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end3 months lateforecast Aug 1, 2021
Also in Charette
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60072 in the federal list. How to read these figures.