Schedule

Announced and approvedJan 27, 2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Charette
Construction start
Aug 28, 2017(actual)
Construction end
Dec 1, 2017(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2016
  • Construction end4 months earlyforecast Mar 31, 2018