Renovation of the schoolyard pavement
Federal contribution
$825,600
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Jun 3, 2021(actual)
- Construction end
- Oct 22, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 1, 2021
- Construction end3 weeks lateforecast Sep 30, 2021
Also in Montréal