Belle River Dredging and West Beach Grading
Federal contribution
$191,200
Federal share80%
of $239.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Lakeshore
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Jan 12, 2023(actual)
Also in Lakeshore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60076 in the federal list. How to read these figures.