Upgrading of backflow prevention devices, meter, water cut-off system and domestic water inlet valve

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$206,400
Federal share80%

of $258.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Aug 20, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2021
  • Construction end2 months earlyforecast Oct 31, 2021

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60105 in the federal list. How to read these figures.