Corridor repair
Federal contribution
$224,000
Federal share80%
of $280.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Nov 2, 2022(actual)
Against the original forecast
- Construction start12 months lateforecast Jun 30, 2021
- Construction end5 weeks lateforecast Sep 30, 2022
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60107 in the federal list. How to read these figures.