Corridor repair
Federal contribution
$258,909
Federal share72%
of $360.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2021
- Construction end6 months lateforecast Dec 15, 2021
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60108 in the federal list. How to read these figures.