Washroom and Entrance Door Retrofits
Federal contribution
$912,854
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Windsor
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Jan 10, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Oct 31, 2022