College Ave Crossing Improvements

Guelph, Ontario

completeActive TransportationCVRIS
Federal contribution
$79,520
Federal share80%

of $99.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Nov 28, 2022(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Sep 30, 2022

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60143 in the federal list. How to read these figures.