Back to projects

Park Infrastructure for Proposed Community Park

Sundridge, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 23, 2021(actual)
Construction end
Aug 24, 2022(actual)

Also in Sundridge