Air Purification of Niagara Region Facilities

Welland, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$720,000
Federal share80%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023202420252026
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2021(actual)
Construction end
Dec 31, 2025(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2026