Growing Outdoor Play in Arnprior - Caruso Park
Federal contribution
$47,589
Federal share80%
of $59.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
202220232024
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Arnprior
- Construction start
- Jul 17, 2023(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction end2 weeks lateforecast Dec 15, 2023
Also in Arnprior
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60162 in the federal list. How to read these figures.