Replacement of windows and partial repair of exterior facings
Federal contribution
$509,480
Federal share80%
of $636.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 25, 2021(actual)
- Construction end
- Jul 18, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2021
- Construction end17 months earlyforecast Dec 31, 2024
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60179 in the federal list. How to read these figures.