Replacement of the water tower

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$967,200
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Jun 30, 2022(actual)