Replacement of the water tower
Federal contribution
$967,200
Federal share80%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de la Pointe-de-l'Île
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Jun 30, 2022(actual)