Richmond Street - Active Transportation Upgrade
Federal contribution
$119,801
Federal share80%
of $149.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Thames Centre
- Construction start
- Sep 16, 2021(actual)
- Construction end
- Nov 29, 2021(actual)
Against the original forecast
- Construction end4 weeks lateforecast Oct 31, 2021
Also in Thames Centre
- Porters Subdivision Watermain Replacement$995.0K
- Engineering Design & Approvals for the Dorchester Wastewater Treatment Plant expansion to 1200 cubic meters capacity$120.0K
- High Lift Pump upgrades recirculation piping in the Dorchester Water Treatment Plant$50.0K
- Water Storage Mixer installations in 3 water storage reservoirs in Dorchester$33.2K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60186 in the federal list. How to read these figures.