Back to projects

Richmond Street - Active Transportation Upgrade

Thames Centre, Ontario

completeActive TransportationCVRIS
Federal contribution
$119,801
Federal share80%

of $149.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 16, 2021(actual)
Construction end
Nov 29, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Oct 31, 2021

Also in Thames Centre

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60186 in the federal list. How to read these figures.