Engineering Design & Approvals for the Dorchester Wastewater Treatment Plant expansion to 1200 cubic meters capacity
Federal contribution
$120,000
Federal share50%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Thames Centre
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Sep 29, 2018