Engineering Design & Approvals for the Dorchester Wastewater Treatment Plant expansion to 1200 cubic meters capacity

Thames Centre, Ontario

completeWastewaterCWWF
Federal contribution
$120,000
Federal share50%

of $240.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 17, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Sep 29, 2018