North Bay City Hall Repairs, Retrofits and Upgrades
Federal contribution
$208,000
Federal share80%
of $260.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of North Bay
- Construction start
- May 10, 2021(actual)
- Construction end
- Dec 29, 2023(actual)
Against the original forecast
- Construction end3 months lateforecast Sep 30, 2023
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60190 in the federal list. How to read these figures.