Schedule

Announced and approvedJun 7, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Thessalon
Construction start
Mar 15, 2023(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jan 1, 2023
  • Construction end4 weeks earlyforecast Oct 31, 2023