Develop a Water Feasibility Study
Thessalon First Nation, Ontario
Federal contribution
$34,877
Federal share50%
of $69.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2017
201820192020
Built
Approved 4 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Thessalon First Nation
- Construction start
- Aug 17, 2018(actual)
- Construction end
- Sep 3, 2020(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 3, 2017
- Construction end10 months earlyforecast Jun 30, 2021