Emergency Back-up Generator Installations
Federal contribution
$176,000
Federal share80%
of $220.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Niagara-on-the-Lake
- Construction start
- Oct 4, 2021(actual)
- Construction end
- Sep 22, 2022(actual)
Also in Niagara-on-the-Lake
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60215 in the federal list. How to read these figures.