Repair of interior finishes
Federal contribution
$227,492
Federal share69%
of $330.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Dec 21, 2021(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2021
- Construction end3 months earlyforecast Mar 30, 2022
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60221 in the federal list. How to read these figures.