Back to projects

Township Active Transportation Improvements

Centre Wellington, Ontario

completeActive TransportationCVRIS
Federal contribution
$240,000
Federal share80%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2022(actual)
Construction end
Oct 28, 2023(actual)

Also in Centre Wellington