Township Active Transportation Improvements
Federal contribution
$240,000
Federal share80%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Township of Centre Wellington
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Oct 28, 2023(actual)
Also in Centre Wellington
- Renovation and Rehabilitation of the Elora Community Centre with an Arena$2.0M
- Replacement of Two Bridges: Structure No. 19-P and No. 25-WG$666.7K
- Mitigation of Inflow and Infiltration (I/I) into Sanitary Sewer and Cast-Iron Watermain Replacement on Churchill Crescent$437.0K
- Trunk Storm Sewer Replacement (Moir Street to the Irvine River) to Reduce Risk of Flooding the Downtown Elora and Nearby Neighbourhood$131.1K
- Inflow and Infiltration (I/I) into Sanitary Sewer Mitigation and Cast-Iron Watermain Replacement on James Street (Forfar Street to Churchill Cres)$90.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60223 in the federal list. How to read these figures.