Mitigation of Inflow and Infiltration (I/I) into Sanitary Sewer and Cast-Iron Watermain Replacement on Churchill Crescent
Federal contribution
$436,986
Federal share36%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
201820192020
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Township of Centre Wellington
- Construction start
- May 14, 2018(actual)
- Construction end
- Aug 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 2, 2018
- Construction end9 months lateforecast Nov 30, 2019
Also in Centre Wellington
- Renovation and Rehabilitation of the Elora Community Centre with an Arena$2.0M
- Replacement of Two Bridges: Structure No. 19-P and No. 25-WG$666.7K
- Township Active Transportation Improvements$240.0K
- Trunk Storm Sewer Replacement (Moir Street to the Irvine River) to Reduce Risk of Flooding the Downtown Elora and Nearby Neighbourhood$131.1K
- Inflow and Infiltration (I/I) into Sanitary Sewer Mitigation and Cast-Iron Watermain Replacement on James Street (Forfar Street to Churchill Cres)$90.5K